Phase I; Jul 17th Construction Update
A message to our neighbors from Pam Krecklow, Real Estate & Construction Manager, Albertina Kerr:
West Gresham
Albertina Kerr Project Phase I; Jul 17th Construction Update
Zimmerman Heritage Farm Tours: Sat Jul 19, 2014 Noon-3PM
![]() 1874 Zimmerman House. Click to Enlarge |
Dog Days of Summer
When: Sat Jul 19, 2014 Noon-3PM |
A delightful 1874 Victorian farmhouse
Take a step back into history at the Zimmerman House, a Victorian era farmhouse, built in 1874 and listed on the National Register of Historic Places. This beautiful farmhouse is a perfect reflection of typical Columbia River dairy farm life in the late 1800s. The Zimmerman Heritage Farm is a unique cultural education and recreational resource that is being created for the benefit of the public on a 5.98-acre historic site in Gresham, Oregon.
Albertina Kerr Project Phase I; Jul 10th Construction Update
Phase I; Jul 10th Construction Update
A message to our neighbors from Pam Krecklow, Real Estate & Construction Manager, Albertina Kerr:
Albertina Kerr Project Phase I; Jul 25th Construction Update
Phase I; Jul 25th Construction Update
A message to our neighbors from Pam Krecklow, Real Estate & Construction Manager, Albertina Kerr:
Greetings, Another week down and things are really starting to come together quickly. The paving got done yesterday and the Subacute main entry is back up and running as scheduled. Guests using the front door now get to use the new sidewalk and see the new front entry that has gone in, not to mention the new driveway and parking lot! Insulation is all in and the drywall is delivered and ready for install. At the residence the B/B court base is in and the new driveway and curbs are looking gorgeous. The drywall and painters got done with the interior of the Residence, they ripped through the walls in a single day. Interior doors were delivered today and are being installed as I write. Coming up: Subacute Residence:Continue interior door and window install, flooring is being installed late next week (if we pass todays moisture test,) plus I hear the B/B hoop is on its way so I wouldn't be surprised to see it up next week. We will also be starting on landscaping too so expect to see some signs of new life starting to pop up here and there as we move through the next few weeks. The 165th sidewalk is out of commission right this minute but Andersen assures me it will get reinstalled ASAP for the neighbors continued use. The construction site and existing fencing are remaining in place until end of project. I still don't have an exact completion date as we continue to try to get done as quickly as possible and that makes it very fluid but we are beginning to discuss furniture and moving so no matter when, it will be here before we know it. Any questions, issues, concerns please just let me know. Pam Krecklow |
WENA Board Meeting: Mon Jun 02, 2014 6:30PM (Rescheduled)
![]() |
May Board Meeting RescheduledWhen: Mon Jun 02, 2014 6:30PM (date change) |
Board meetings are scheduled for the 4th Monday each month 6:30PM
For more information please contact: info@wilkeseastna.org
Upcoming Meetings
- Jun 23, 2014
- Jul 28, 2014
- Aug 25, 2014
Albertina Kerr Project Phase I; Jun 20th Construction Update
Phase I; Jun 16th Construction Update
A message to our neighbors from Pam Krecklow, Real Estate & Construction Manager, Albertina Kerr:
Greetings,
It has been pretty much a mixed bag this week. Some good news, some bad but in spite of it all we just keep moving forward. The best news is the design application is in for the Louise Building! Plus I got a contingent of Subacute staff through for a tour of the new addition. They are so excited there were tears! Bad news is we are discussing a small delay in schedule on Residence and Subacute, possibly out 2 additional weeks to mid-August. But don't believe that just yet as the team is working hard to make that NOT happen. So we will see where we end up on it. More as we move forward.
This week wasn't real exciting, just finishing up a bunch of elements on the exteriors and still, yes, still pulling wire on the interior. Equipment has started to arrive and duct work is going in. Subacute' s main art install has been finished by Art from the Heart and is ready for pick up and their finishes are almost picked out, the paint can be a hard one. If your by my desk take a look.
Next week...
Subacute:
Gym shut down Wednesday morning for a couple of hours for NW Natural gas exploration, initial part of the equipment tie in which we all know is coming.
We made it through the last of the fire system testing, all the remaining parts of the existing system held (phew, no more floods) and the system remained pressurized for two hours for the test so we passed inspection. The only issue was the Fire Marshal didn't like the hose size we used to flush the system once we were done so we will have to flush the system one more time. A minor inconvenience on that one.
- Finishing up the flat roofing at the exterior mechanical area
- Continuing interior insulation and walls
Residence:
Looking at PGE power install here in just a bit. This install will have some effect on parking around Multnomah CI but transport will remain flowing. More to come on this as we move forward.
- Will begin to see painting on the exterior
- Have the insulation in
- Drywall install in progress
Louise:
Working on Seismic Upgrade plan
Parking plan remains the same. Likely won't have an update next week with it being short and the holiday and all but will make sure I keep everyone in the loop. If you don't hear from me before, y'all have a great holiday.
Any questions, issues, concerns please just let me know.
Pam Krecklow
Albertina Kerr
Albertina Kerr Project Phase I; Jun 16th Construction Update
Phase I; Jun 16th Construction Update
A message to our neighbors from Pam Krecklow, Real Estate & Construction Manager, Albertina Kerr:
If you haven't seen the site lately is really coming along: Residence: Subacute: That is pretty much it, as I said earlier the WOW elements are pretty much done. But we are moving forward. Parking remains as depicted on plan. Any questions, issues, concerns please just let me know. Pam Krecklow |
Albertina Kerr Project Phase I; Jun 1st Construction Update
Phase I; Jun 1st Construction Update
A message to our neighbors from Pam Krecklow, Real Estate & Construction Manager, Albertina Kerr:
The safety glass is designed to withhold (5) 50lb drops of a steel ball. The State (of Oregon) was by to walk through the new Residence and everyone is very excited to see it come to fruition. The Subacute addition (right foreground) is framed-in and the interior walls are up. It's becoming quite the space. Been working with everyone on interior colors and finishes, will have them buttoned up here in the next couple of weeks. Always a good sign there is an end in sight, as getting the finishes/color in is one of the last things to do. This next week expect:
All the dramatic drama is pretty much over, at least until the end of this month when we start to finish up the site work. A heads-up to Subacute, tie in to existing equipment (plumbing, electrical, mechanical/furnace, fire system, etc.) is going to be starting in earnest in the next couple of weeks. I am sorry to say this will be a big inconvenience, as it will means guys in the hallways (mainly therapist hallway but gym hallway also) and some noise. The residence wings will remain free of physical disturbance but circulation throughout the building will be impacted. There is no reason to panic, this is just a heads up it is on the way. I don't have any specifics yet but as soon as I do we will be working through scheduling and all the other issues to make it as convenient and painless as we possibly can. If you need any incentive to get you through this next part, just go out and look at the addition. It is going to be fabulous! No changes in parking this next week and there remains parking available up and around the Louise Building. One more week down, only nine more to go! Any questions, issues, concerns, please let me know. Pam Krecklow |
Free! Rock the Block Festival 2014: Fri Jun 27, 2014 3PM-8PM
![]() |
Join the fun on the plaza!When: Fri Jun 27, 2014 3PM-8PM |
Everyone's Invited!
Join us June 27 and 28 for Rock the Block, an engaging, family-oriented community celebration that enables neighborhood residents to:
- Enjoy safe family fun
- Nutritious food
- Access and enroll in needed services
- Change their environment for the better via positive social engagement
Rock the Block also provides a forum for the community to connect to youth activity and resource providers in the area and thrive on an ongoing basis. Festival Poster
Read more about Rock the Block as well as event volunteer opportunities.
Zimmerman Heritage Farm Tours: Sat May 17, 2014 Noon-4PM
![]() 1874 Zimmerman House. Click to Enlarge |
Welcome Spring
When: Sat May 17, 2014 Noon-4PM |
A delightful 1874 Victorian farmhouse
Take a step back into history at the Zimmerman House, a Victorian era farmhouse, built in 1874 and listed on the National Register of Historic Places. This beautiful farmhouse is a perfect reflection of typical Columbia River dairy farm life in the late 1800s. The Zimmerman Heritage Farm is a unique cultural education and recreational resource that is being created for the benefit of the public on a 5.98-acre historic site in Gresham, Oregon.