Land use

Albertina Kerr Project Phase I; May 2nd Construction Update

Albertina Kerr Begins Construction on $1.5M Project in West Gresham. Phase I; April May 2nd Construction Update. Info here!

Phase I; April May 2nd Construction Update
A message to our neighbors from Pam Krecklow, Real Estate & Construction Manager, Albertina Kerr:

Greetings,

No flooding this week, but we have had wood flying! The crane was here pulling trusses off the truck and up onto the new walls of the residence. Always exciting to see that.

Albertina Kerr Project Phase I; New Residents Facility Takes Shape
Albertina Kerr, New Residents Facility

This week's activities also included:

  • Temporary fence moved at Subacute - It didn't rain for me but we only had to have the playground down Thursday morning & Friday to mid-afternoon so everyone got to enjoy the sunshine while it is here.
  • Slab poured for Subacute - Contractor was happy it didn't rain too.
  • Finished up most of the messy demo at the Louise, there will still be activity but not major activity.

Next week is another big week:

  • We start the week by building a new temporary exterior wall in Subacute so that we can begin the tie in to the existing building. Expecting to only have the group room out of commission for about 4 hours and then we will be out of staffs hair. Although, keep in mind there will still be outside noise this next week as we demolish some of the existing building's exterior but hoping to be quick.
  • Will finish the framing on the residence and begin framing the Subacute expansion. We have two more delivery of trusses for the expansion so more big trucks next week.
  • Contractor didn't get the Cold Storage Building demolished, had to pull equipment for an emergency in Eugene, but will be addressing on Monday and then we will finish up the well decommissioning so expect activity around that area most of next week. Luckily we moved the fence so the playground can remain open.

Future Attractions:

  • Things will remain fast and furious for another week or two as we finish up framing and then it will subside to a snail's pace as we move into the interior, so enjoy it while you can.
  • This also means that will have to begin equipment tie in. This is a couple weeks out but putting it on everyone's radar as it will be yet another inconvenience for Subacute. Again a couple weeks out yet, so no reason to panic as we will work out plans prior to doing any work.

Please remember that we can park all over campus, so even if there is no parking close to your building there is parking somewhere on Campus. The parking plan is still valid. After the last of the trusses are delivered we will be able to open up some additional parking which will relieve any pressure.

As always a huge thanks for being patient and understanding as all the pieces fall into place. I am exhausted after another busy week but got to walk through the new residence today and although ready to collapse, am very excited to see it all coming together.

Pam Krecklow
Albertina Kerr

Albertina Kerr Project Phase I; April 18th Construction Update

Albertina Kerr Begins Construction on $1.5M Project in West Gresham. Phase I; April 18th Construction Update. Info here!

Phase I; April 18th Construction Update
A message to our neighbors from Pam Krecklow, Real Estate & Construction Manager, Albertina Kerr:

Greetings,

Another week down
I readily admit not a lot to see for it but all the work being done now will pay huge rewards in the future by creating strong and durable foundations for the buildings. We had a lot of inspections this week of all the plumbing, electrical, and mechanical elements that are under the foundation slabs and because the construction crew is so good, we have passed them all.

Fire Marshall has also been on campus a lot this week testing fire hydrants and preparing for moving the Sub Acute's underground Fire/Water vault. Yes this means that next week will be full of inconvenience as we are needing to turn off the water to Sub Acute on Tuesday for the day. I have my fingers crossed for 4 hours but the contractor feels it will take them closer to 8 hours to get all the piping out of the existing fire/water vault, pull the existing vault, install a new reinforced vault, and reconnect everything. We have a contingency plan for 12 hours just to be safe. Be sure to be especially kind to Sub Acute staff as they are taking one for the team this next week and in their usual way are approaching it with positivity, flexibility, and tons of grace.

We were not able to pour the slab for the new residence this week but will be doing it on Monday. I know it will be tempting to see all that fresh concrete and want to put your initials in it but construction crews will be watching closely plus we do have some web cams up -- can't say you weren't warned.

Other elements to expect next week
Residence concrete slab on Monday, will need to cure for at least 3 days Joint Board and Foundation Board meeting in Chapel Monday evening Install of new Fire/Water vault on Tuesday Framing will begin on Residence on Thursday (yeah man, we are going vertical!) Delivery of big items like lumber & roof trusses will begin Louise Building interior demo will continue through the week Expect Project Manager collapse by end of week

In the near future expect
Some hammering as we move to framing and roofing More concrete poured as we pour the Sub Acute slab the 29th Numerous big trucks delivering lots of materials Demo of the Cold Storage Building which means more fence work at Sub Acute

As always if you have any issues, questions, or are just curious let me know.

Pam Krecklow
Albertina Kerr

Albertina Kerr Project Phase I; April 11th Construction Update

Albertina Kerr Begins Construction on $1.5M Project in West Gresham. Phase I; April 11th Construction Update. Info here!

Phase I; April 11th Construction Update
A message to our neighbors from Pam Krecklow, Real Estate & Construction Manager, Albertina Kerr:

Greetings,

Well it has been a full week:

  • The change in weather has allowed us to get the first concrete pour done, which means we have footings.....yeah!
  • We got the new North driveway cut in.
  • Sub Acute's entrance got shifted from the South side of the building to the North side. Yes it's different but you get a great view of the construction site.
  • IT's (information technology) fiber work got completed so that project is done and the road between Louise and Sub Acute is open again.
  • We started the decommissioning process on the old well, which is beside the cold storage building.
  • We began interior demolition of the Louise Building, we aren't doing anything on the outside so all you will see is a bunch of stuff (including some horse hair plaster, yes that's how they made plaster back in 1925) being tossed into dumpsters.

Next week expect:

  • More concrete trucks, we will begin pouring our slabs which after those cure we will be going vertical.....the really exciting stuff!
  • We will be working on the area along 165th and the new emergency entrance to campus.
  • Coming Soon:

    • A new fire/water vault will be going in soon. Yes I am the only one probably excited about this one but it is a huge hurdle. This work will cause some issues for Sub Acute when it happens but we are working up plans to address all contingencies.

    As always if you have any issues, questions, or are just curious let me know.

    Pam Krecklow
    Albertina Kerr

Albertina Kerr Project Phase I; April 4th Construction Update

Albertina Kerr Begins Construction on $1.5M Project in West Gresham. Phase I; April 4th Construction Update. Info here!

Phase I; April 4th Construction Update
A message to our neighbors from Pam Krecklow, Real Estate & Construction Manager, Albertina Kerr:

Greetings,
As expected it was a pretty quiet this week. In spite of the rain we have been able to finish the trenching, pipe install, and slab layout. We have also made great process on installing rebar and the concrete forms. IT (information technology) has also been working on installing some fiber lines which is the work that has been happening on the road way behind the Louise Building.

Next week we can expect:

  • A new entrance into Sub Acute, we will be shifting the temporary entrance to the North side of the building versus were it is on the South side currently. Look for that to be open when you get to campus on Thursday the 10th.
  • The new Sub Acute entrance is allowing us to cut the new driveway in earlier than expected, keep in mind this is just forming it. We are not opening the driveway until we are done with construction.
  • Decommissioning of the old well that is adjacent to the Cold Storage Building (expecting that on Monday the 7th)
  • And yes we should have some concrete next week also.

Still excited as we will soon see some vertical elements happening as we move on to framing.

The parking will remain as depicted on the parking map. A new version is attached that reflects the new Sub Acute entrance but parking areas have not changed.

As always if you have any questions, concerns, or issues please let me know so the project team can get a solution.

Pam Krecklow
Albertina Kerr

Albertina Kerr Project Phase I; April 27th Construction Update

Albertina Kerr Begins Construction on $1.5M Project in West Gresham. Phase I; April 27th Construction Update. Info here!

Phase I; April 27th Construction Update
A message to our neighbors from Pam Krecklow, Real Estate & Construction Manager, Albertina Kerr:

Greetings,

As expected last week was just full of activity but the good news is everyone made it through without a scratch, expect for a buried 8" pipe.

A recap of last week activities included:

  • The 2014 flood, which was caused by a failed pipe fitting and all that water had to go somewhere. Just glad we got it stopped before entering the Sub Acute facility but it was a close one
  • This event did cause Sub Acute's water to be shut off for an additional day but we did get rid of port a potties on Thursday (YEAH)
  • Plus between Rockwood Water District and the Contractor (yes it took both of them) we did have to have flush the whole neighborhoods water system to clean it out late Tuesday night. This was pre flood but a huge inconvenience for the whole neighborhood
  • Water is back on and we have had no trouble since 4/23/14 so I am putting the flood and the sleepiness night behind me and moving forward
  • We did get exterior supports up on the Louise Building
  • And did start framing, WE HAVE WALLS. If you haven't seen them yet take a second and check it out.

Next week will be equally busy. Expect lots of activity as we:

  • Continue framing the new residence
  • Pour the slab for the Sub Acute addition (Tuesday). Again there are web cams up if anyone is tempted
  • We are expecting the residence roof trusses to be delivered on Wednesday
  • Will be taking the Cold Storage Building down this week also
  • Cold Storage Demo will affect the Sub Acute playground late in the week as we are moving the West fence in an attempt to make up some square footage that was lost when we adjusted the North fence. I am hoping for rain Thursday and Friday, sorry
  • We will be finishing up the interior demo at the Louise but still have some mitigation, wiring, and misc. elements to address so not done yet
  • Might (although it is a big might) see a wall or two appear for the Sub Acute expansion

Just a heads up but coming up in the near future:

  • The cut into the Sub Acute building. We will begin discussion this next week on schedule and plan just letting everyone know more is coming. Believe it or not there is an end in sight.
  • Lots for hammering as we begin framing on both buildings

Can't thank everyone, especially the neighbors, enough for their patience and support this last week. It was a trying one for everybody yet everyone, but me, handled the water shut down, flood, and resulting issues with so much grace that it warmed my heart. A huge thank you to everyone. If you have any questions, concerns, issues, or etc. please don't hesitate to give me a call.

Pam Krecklow
Albertina Kerr

Historic Gresham Pioneer Cemetery Tour: Sat Nov 16, 2013 11AM-12PM

11/16/2013 - 11:00am
11/16/2013 - 12:00pm
Etc/GMT-8

Historic Gresham Pioneer Cemetery Tour: Sat Nov 16, 2013 11AM-12PM. Info here!

When: Sat Nov 16, 2013 11AM-12PM
Where: Meet at Main City Park
Spring Water Corridor entrance
Gresham OR
Get Map!

Tour Gresham's Pioneer Cemeteries
Join us for a walk through history as we wind our way through Gresham's Pioneer Cemeteries.

We'll visit some of Gresham's historically significant graves and learn a little about the lives of those within them.

The tour group will meet at the Spring Water Corridor entrance into Main City Park. From there the group will walk a short distance to the Pioneer Cemeteries.

The tour is absolutely free.

Gresham City Council to consider rule changes for food carts, temporary uses: Tue Oct 01, 2013 6PM

10/01/2013 - 6:30pm
Etc/GMT-8
Gresham City Council to consider rule changes for food carts, temporary uses: Tue Oct 01, 2013 6PM. Info here!

Public input welcome

When: Tue Oct 01, 2013 6:30PM
Where: Gresham City Hall
1333 NW Eastman Pky
Gresham OR
Get Map!

Gresham is updating its rules for food and beverage carts (coffee carts, mobile food vendors, taco trucks) and temporary uses (farmers' markets, Christmas tree lots, fruit and veggie stands, and similar uses).

The City Council will consider changes to rules, processes, fees and inspections at its 6 p.m. Oct. 1 meeting. Public comments are welcome.

Changes include:

  • Sorting uses into four categories: Temporary, Intermittent, Interim and Food and Beverage Carts
  • New definitions.
  • Clarify where uses are permitted.
  • Establish safety rules, including for lighting, site ingress and egress, pedestrian hazards, fire separation and rules for drive-throughs.
  • Set compatibility rules, including for setbacks, increased distance from residential uses, adequate parking and bathrooms for food service uses.
  • Provide appearance rules, including for signage; screening; maintenance; quality of shelter for customers; and not allowing food carts in motorized vehicles if they are to remain on a site for more than four hours.

All meeting locations are ADA accessible.

Central Rockwood Plan Update July 2013 Community Forum: Jul 17, 2013 6PM-8PM

07/17/2013 - 6:00pm
Etc/GMT-8
Central Rockwood Plan Update July 2013 Community Forum: Jul 17, 2013 6PM-8PM. Info here!

Redefining Rockwood

When: Wed Jul 17, 2013 6PM-8PM
Where: Gresham City Hall
1333 NW Eastman Pkwy
Get Map!

Join us to review alternative approaches to issues identified by the Central Rockwood Plan Update project. Issues include standards for mixed-use development, building heights, residential densities and the development of deep lots. Staff wants your opinion on what alternative approaches you prefer and why.

The forum will include:

  • 6 p.m. Open House
  • 6:15 p.m. Presentation
  • 6:35 p.m. Small Group Sessions
  • 7:15 p.m. Group Reporting
  • 7:30 p.m Conclusions and Next Steps

Rescheduled Food Cart / Temporary Uses Open House: Jun 26, 2013 6PM-8PM

06/26/2013 - 6:00pm
06/26/2013 - 8:00pm
Etc/GMT-8
City of Gresham, Food and Beverage Carts Open House and Community Forum:  Jun 26, 2013 6PM-8PM. Info here!

Come Review Proposed
Rule Changes

When: Wed Jun 26, 2013 6PM-8PM
Where: Gresham City Hall
1333 NW Eastman Pky
Gresham OR
Get Map!

Mark your calendar for this food cart/temporary uses event

Third Time's A Charm
Come to June meeting to review proposed rule changes

Gresham is considering updating its rules for food and beverage carts (coffee carts, mobile food vendors, taco trucks) and temporary uses (farmers' markets, Christmas tree lots, fruit and veggie stands, and similar uses).

The originally scheduled May 6th & rescheduled May 23rd, this open house has been rescheduled again for June 26th.

Come to the June 26 open house to review the draft rule changes (Development Code updates)and fee revisions for both food carts and temporary uses. The open house is scheduled for 6PM-8PM. Drop in anytime to provide your comments.

Early Neighborhood Meeting on Proposed Nadaka Neighborhood Park Land Use/Development Application: Tue Apr 16, 2013 7PM

04/16/2013 - 7:00pm
Etc/GMT-8
Early Neighborhood Meeting on Proposed Nadaka Neighborhood Park Land Use/Development Application: Tue Apr 16, 2013 7PM. Info here!
Nadaka Nature Park, Gresham OR

Early Neighborhood Meeting

When: Tue, Apr 16, 2013 7PM
Where: St Aidan’s Episcopal Church
17405 NE Glisan St
Gresham OR
Get Map!

You're Invited
This meeting is being held to discuss a proposed project; Nadaka Neighborhood Park, located adjacent to St. Aidan’s church. The property can be legally identified as (Site ID numbers 1N3E1AC9700, 10000,10100, and tax lot numbers R943310160, R943310520 and R943311370).

This project is in the Wilkes East Neighborhood Association. You can see pre-application notes for this proposal at https://egov.greshamoregon.gov/Click2GovPZ/. It is Pre-Application Conference Number PAM13-26000040.

Purpose of meeting is to provide an opportunity for applicant and surrounding property owners to meet and discuss this proposal. Proposed park improvements expand existing trail and pathway system, children’s nature play area, community garden, berry patches, picnic shelter, seating and restrooms.

Syndicate content